Burnt rock water control scheme in Jiangjun Gobi No.2 Open-pit Coal Mine stope north slope

  

  • Online:2016-05-15 Published:2016-05-10

将军戈壁二号露天煤矿采场北帮烧变岩水治理方案

  

Abstract:

Abstract According to the actual geological situation in Jiangjun Gobi No.2 Open-pit Coal Mine, the article analyzed compared three technical schemes of the curtain grouting, water drainage and curtain drainage. The author thought the curtain grouting was feasible under the geological conditions, which greatly reduced the investment and the production cost of waterproof and drainage, and was beneficial to the slope stability, and provided water security for Jiangjun Gobi No.2 Open-pit Coal Mine development.

摘要:

摘 要:根据将军戈壁二号露天煤矿实际地质情况,分析对比帷幕注浆、疏干排水及帷幕疏干相结合3种技术方案,认为帷幕注浆在该地质情况下可行,极大的降低了防排水资金投入及生产成本,有利于边坡稳定,并为今后将军戈壁二号露天煤矿发展提供水源保障。