平朔东露天矿过陷落柱开采方案研究
Abstract:
Abstract:The article presents two collapse columns based on the actual situation of the worksite in order to make collapsed column production organization and security work well in Pingshuo East Open-pit mine. Collapse column bridge scheme can not only decrease the rock stripping and reduce production safety risk, but also facilitate the form of internal waste dump by comparasion.
摘要:
摘 要:为做好平朔东露天矿过陷落柱的生产组织和安全工作,根据现场实际情况提出了2种过陷落柱方案。经对比过陷落柱搭桥方案不仅可以减少岩石剥离量,降低生产安全风险,同时便于内排土场形成。
Duan Lishi, HAN Jin, XU Jun. Mining scheme research of collapse column in Pingshuo East Open-pit Mine[J]. 露天采矿技术.
段力士,韩进,徐君 .
平朔东露天矿过陷落柱开采方案研究[J]. 露天采矿技术.