Abstract:

Abstract: Through comparatively researching two kinds of shift schemes of semi-continuous system in Zhahanao'er Open-pit Mine, the mine rationally distributes semi-continuous dumping system and single bucket truck operation area, which increases effective internal dumping space, reduces production cost and improves economic benefit.

摘要:

 

摘 要:通过对扎哈淖尔露天矿半连续工艺2种移设方案对比研究,将半连续排土系统与单斗-卡车工艺作业区域进行合理化分配,增加了有效内排空间,降低了生产成本,提高了经济效益。